Permit Extension Act

Please be aware that the Permit Extension Act is expiring on December 31, 2015. The clock will begin to run again on January 1, 2016 and no approvals will extend beyond June 30, 2016 unless the approval would have extended beyond June 30, 2016 without the benefit of the Act.  If you have an approval that it is on the verge of expiring, you might be wondering what the next steps should be.  In general, your two options are to either start the project or request an extension from the board or agency which granted the approval.

With regard to calculating time frames of an approval, please see the following (assume the life of the approval is for 1 year):

_____________________________________________________

 

Date of Approval                                                                                Expiration of Approval

April 1, 2006                                                                                       March 31, 2016

June 10, 2009                                                                                      June 30, 2016

December 30, 2014                                                                             December 30, 2016

_____________________________________________________

If you would like to discuss the correct approach concerning your approval, please contact us at 201-587-0888.

– Andrew S. Kohut, Esq.