MAIN OFFICE:
12 North Route 17,
P.O. Box 1827
Paramus, New Jersey 07653-1827
Phone: (201)587-0888
Fax: (201)587-8845
Email:
attorney@wellslaw.com

SATELLITE OFFICES:
New York City Law Office
1040 Avenue of the Americas - 24th Flr.
New York, NY 10018
(212) 847-9560

Morristown, New Jersey Law Office
55 Madison Avenue, Suite 400
Morristown, NJ 07960
(973) 285-3360

Bristol, Vermont Law Office
25 D Main Street
Bristol, VT 05443
Phone: (802)453-5765
Fax: (802) 329-2100

Lyndhurst, New Jersey Law Office
10 Stuyvesant Ave
Lyndhurst, New Jersey 07071
(201) 531-8989

Tuckerton, New Jersey Law Office
149 E. Main Street,
Tuckerton, New Jersey 08087
(609) 296-6666

Click here for Directions

Newsroom

Search:
New Jersey Stimulus For Development
By: James E. Jaworski, Esq. &
Andrew S. Kohut, Esq.

Just last summer, the statewide Nonresidential Development Fee Act was enacted on July 17, 2008. The Act preempted any municipal affordable housing or “COAH” fee ordinance and mandated that any nonresidential development be assessed a fee equaling 2.5% of the equalized assessed value of the improvements and land of the new development (the “2.5% Fee”). The timing could not have been worse, considering the direction of the overall economy and development in particular.

Recognizing the chilling effect this 2.5% Fee had on development, on July 27, 2009, Governor Corzine signed the “New Jersey Stimulus Act of 2009” (the “Stimulus Act”). The Stimulus Act seeks to fuel nonresidential development by exempting certain development from the 2.5% Fee, specifically nonresidential property in which a site plan has received preliminary approval or final approval prior to July 10, 2010, as long as a permit for the construction is issued from the local enforcing agency prior to January 1, 2013.

While there are other esoteric provisions that create exceptions, certainly, this provision will have the greatest impact on our development clients. Hopefully, it will also renew interest in nonresidential development in the State and, ultimately be a key to the success of the Stimulus Act. By expanding the exemption to development approved prior to July 10, 2010, the State is hoping that an influx of development will occur immediately and developers will seek to begin construction instead of delaying already approved projects due to the economic climate.

But, the Stimulus Act states exemptions do not apply to a COAH contribution that a developer “made or committed itself to make prior to the July 17, 2008”. Thus, municipal COAH ordinances in effect prior to the imposition of the 2.5% Fee remained in tact.

Reimbursement of Past Fees

Another key component of the Stimulus Act is the provision for reimbursement of  the 2.5% Fee, or a portion thereof, for any developer who has previously paid a financial contribution to a municipality. The key date in the manner of which the  Stimulus Act calculates the reimbursement is July 17, 2008. The reimbursement of the COAH Fees will be calculated as follows:

  1. Any nonresidential property in which a site plan has received preliminary or final approval prior to July 17, 2008 and was subject to a COAH fee will be entitled to a reimbursement of the difference between monies committed prior to July 17, 2008 and the 2.5% Fee.

  2. A developer of a nonresidential project that paid the 2.5% Fee subsequent to July 17, 2008 will be entitled to a full refund of those monies, with very limited exceptions.


To be clear, understand that this new law does not include a full reimbursement of the 2.5% Fee unless the entire 2.5% Fee was paid after July 17, 2008. If, for example, the developer paid, or committed to pay (either through a Resolution of Approval or more likely an executed Developer's Agreement), a 2.0% Fee prior to July 17, 2008 and subsequently paid an additional 0.5% in accordance with the 2.5% Fee law, only a reimbursement of that subsequent 0.5% would be in order. Furthermore, the language of the Stimulus Act seems to imply that a developer is still responsible to make a payment committed to prior to July 17, 2008,  even if that payment has not been made yet. A client who committed to pay the 2.5% Fee after July 17, 2008, but has not made a payment, will not be responsible for that payment if the proposed development is completed in accordance with the Stimulus Act.

In order to receive a reimbursement of this fee, a written claim must be filed with the entity that received the fee with a copy to the New Jersey Division of Revenue within 120 days of the effective date of this Act. We understand the last date to file such a claim will be November 30, 2009. The municipality must repay the fee within 30 days of receipt of the request under the Stimulus Act. Municipalities may be reimbursed through the New Jersey Affordable Housing Trust Fund.

We will keep you apprised of any further developments in this regard. Feel free to call with specific inquiries.

James E. Jaworski is a Senior Partner at WJ&L. He also heads up our Real Estate Department and actively practices in Land Use and Development areas.

Andrew S. Kohut is an Associate at WJ&L who is active in the Land Use and Real Estate areas of our practice. 

 

© Copyright Wells, Jaworski & Liebman, LLP. All rights reserved.
Home | About Us | Areas of Practice | Attorneys | Newsroom | Clients | Contact Us | Privacy Policy | Directions | Sitemap